Last week at the University Boulevard construction site, Schiralli Construction Corporation laid aggregate base, poured driveways, and continued work on the remainder of the south lane.
Due to wet conditions caused by recent rainfall, the south lane is now scheduled to be poured on Thursday, weather permitting. Other tasks planned for this week include prepping for sod and removing construction debris from the site.